YP.INS.DUVAR.010Supply and placement of lintel

Market Work Item · Construction · DUVAR

Original Turkish name: Lento yapımı ve yerleştirilmesi (yerinde imalat)

Item No.YP.INS.DUVAR.010
Unitm
ClassStandard
Estimated Unit Cost795,49 TL/mexcl. VAT

Scope

Supply of ready (precast) lintel above doors/windows and placing it with mortar.

Components (9) · Quick Estimate

TypeNameUnitQty/mUnit Price (TL)Amount (TL)
MaterialRepair mortarkg64,14192,42
LabourPlasterersaat466,67280,00
LabourUnskilled laborersaat333,33166,67
MaterialGrey cement (bagged)kg3,5017,50
MaterialSand, bulk1.500,0012,00
MaterialCrushed stone no. 1-5, bulk950,009,50
MaterialDeformed reinforcing steel bar Ø8-Ø12ton28.666,6786,00
MaterialFormwork timber (pine, 2nd class)9.166,6727,50
MaterialFormwork nailkg78,113,91
Subtotal (excl. VAT)795,49 TL
VAT (%20)159,10 TL
Grand Total954,59 TL

Component quantities are defaults; adjust them to your own job.

Items in the Same Group

YP.INS.DUVAR.001Autoclaved aerated concrete (AAC) wall construction (10 cm)()
YP.INS.DUVAR.002Brick wall construction (13.5 cm)()
YP.INS.DUVAR.003Pumice block wall construction (15 cm)()
YP.INS.DUVAR.004Glass block wall construction()
YP.INS.DUVAR.005Opening a door/window void in a wall(adet)
YP.INS.DUVAR.006Brick wall laying (19 cm)()
YP.INS.DUVAR.007Autoclaved aerated concrete (AAC) wall laying (15 cm)()
YP.INS.DUVAR.008Autoclaved aerated concrete (AAC) wall laying (20 cm)()
YP.INS.DUVAR.009Pumice block wall laying (20 cm)()
YP.INS.DUVAR.011In-wall tie beam concrete(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.