Market Work Item · Construction · DUVAR
Original Turkish name: Gazbeton duvar örülmesi (10 cm)
| Item No. | YP.INS.DUVAR.001 |
| Unit | m² |
| Class | Standard |
| Estimated Unit Cost | 606,44 TL/m²excl. VAT |
Building partition walls with AAC blocks (excluding plaster).
| Type | Name | Unit | Qty/m² | Unit Price (TL) | Amount (TL) |
|---|---|---|---|---|---|
| Material | AAC block 10 cm | m² | 279,17 | 287,55 | |
| Material | AAC mortar | kg | 7,04 | 28,16 | |
| Labour | Plasterer | saat | 466,67 | 210,00 | |
| Labour | Unskilled laborer | saat | 333,33 | 66,67 | |
| Tool | AAC saw | adet | 1.000,00 | 10,00 | |
| Tool | Notched trowel (AAC block) | adet | 408,25 | 2,04 | |
| Tool | Spirit level | adet | 405,70 | 2,03 | |
| Subtotal (excl. VAT) | 606,44 TL | ||||
| VAT (%20) | 121,29 TL | ||||
| Grand Total | 727,73 TL | ||||
Component quantities are defaults; adjust them to your own job.
Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.
Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.