YP.INS.DUVAR.007 — Autoclaved aerated concrete (AAC) wall laying (15 cm)

Market Work Item · Construction · DUVAR

Original Turkish name: Gazbeton duvar örülmesi (15 cm)

Item No.YP.INS.DUVAR.007
Unitm²
ClassStandard
Estimated Unit Cost853,62 TL/m²excl. VAT

Scope

Laying walls with 15 cm AAC blocks; thin bed mortar is included.

Components (7) · Quick Estimate

TypeNameUnitQty/m²Unit Price (TL)Amount (TL)
MaterialAutoclaved aerated concrete (AAC) block 15 cmm²481,25495,69
MaterialAAC mortarkg7,4437,20
LabourPlastererhr466,67233,34
LabourUnskilled laborerhr333,3373,33
ToolAAC sawpcs1.000,0010,00
ToolNotched trowel (AAC block)pcs408,252,04
ToolSpirit levelpcs405,702,03
Subtotal (excl. VAT)853,62 TL
VAT (%20)170,72 TL
Grand Total1.024,35 TL
AAC saw (Abay) — Buy ↗Notched trowel (AAC block) (Abay) — Buy ↗Spirit level (Stanley) — Buy ↗

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.DUVAR.001Autoclaved aerated concrete (AAC) wall construction (10 cm)(m²)
YP.INS.DUVAR.002Brick wall construction (13.5 cm)(m²)
YP.INS.DUVAR.003Pumice block wall construction (15 cm)(m²)
YP.INS.DUVAR.004Glass block wall construction(m²)
YP.INS.DUVAR.005Opening a door/window void in a wall(adet)
YP.INS.DUVAR.006Brick wall laying (19 cm)(m²)
YP.INS.DUVAR.008Autoclaved aerated concrete (AAC) wall laying (20 cm)(m²)
YP.INS.DUVAR.009Pumice block wall laying (20 cm)(m²)
YP.INS.DUVAR.010Supply and placement of lintel(m)
YP.INS.DUVAR.011In-wall tie beam concrete(m)
YP.INS.DUVAR.012Wood panelling (lambri), interior (pine, grade 1)(m²)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.