YP.INS.DUVAR.003Pumice block wall construction (15 cm)

Market Work Item · Construction · DUVAR

Original Turkish name: Bims blok duvar örülmesi (15 cm)

Item No.YP.INS.DUVAR.003
Unit
ClassStandard
Estimated Unit Cost548,20 TL/m²excl. VAT

Scope

Building walls with pumice blocks (excluding plaster).

Components (7) · Quick Estimate

TypeNameUnitQty/m²Unit Price (TL)Amount (TL)
MaterialPumice block 15 cmadet11,0093,50
MaterialBrick and pumice block laying mortarkg5,86117,20
LabourPlasterersaat466,67233,34
LabourUnskilled laborersaat333,3393,33
ToolSteel troweladet481,102,41
ToolAluminium straight edge 2 madet2.374,584,75
ToolMortar tubadet734,963,67
Subtotal (excl. VAT)548,20 TL
VAT (%20)109,64 TL
Grand Total657,84 TL
Steel trowel (Dekor)BuyAluminium straight edge 2 m (Rox)BuyMortar tub (Dekor)Buy

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.DUVAR.001Autoclaved aerated concrete (AAC) wall construction (10 cm)()
YP.INS.DUVAR.002Brick wall construction (13.5 cm)()
YP.INS.DUVAR.004Glass block wall construction()
YP.INS.DUVAR.005Opening a door/window void in a wall(adet)
YP.INS.DUVAR.006Brick wall laying (19 cm)()
YP.INS.DUVAR.007Autoclaved aerated concrete (AAC) wall laying (15 cm)()
YP.INS.DUVAR.008Autoclaved aerated concrete (AAC) wall laying (20 cm)()
YP.INS.DUVAR.009Pumice block wall laying (20 cm)()
YP.INS.DUVAR.010Supply and placement of lintel(m)
YP.INS.DUVAR.011In-wall tie beam concrete(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.