YP.INS.DUVAR.005Opening a door/window void in a wall

Market Work Item · Construction · DUVAR

Original Turkish name: Duvarda kapı/pencere boşluğu açılması

Item No.YP.INS.DUVAR.005
Unitadet
Estimated Unit Cost2.955,22 TL/adetexcl. VAT

Scope

Opening an opening in a non-load-bearing wall and installing a lintel.

Components (11) · Quick Estimate

TypeNameUnitQty/adetUnit Price (TL)Amount (TL)
MaterialRepair mortarkg64,14962,10
LabourPlasterersaat466,67933,34
LabourUnskilled laborersaat333,33666,66
MachineryElectric rotary hammeradet3.860,28193,01
ToolMoil point and chisel setadet236,3311,82
MaterialGrey cement (bagged)kg3,5021,00
MaterialSand, bulk1.500,0015,00
MaterialCrushed stone no. 1-5, bulk950,0011,40
MaterialDeformed reinforcing steel bar Ø8-Ø12ton28.666,67103,20
MaterialFormwork timber (pine, 2nd class)9.166,6733,00
MaterialFormwork nailkg78,114,69
Subtotal (excl. VAT)2.955,22 TL
VAT (%20)591,04 TL
Grand Total3.546,26 TL
Electric rotary hammerBuyMoil point and chisel set (Einhell)Buy

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.DUVAR.001Autoclaved aerated concrete (AAC) wall construction (10 cm)()
YP.INS.DUVAR.002Brick wall construction (13.5 cm)()
YP.INS.DUVAR.003Pumice block wall construction (15 cm)()
YP.INS.DUVAR.004Glass block wall construction()
YP.INS.DUVAR.006Brick wall laying (19 cm)()
YP.INS.DUVAR.007Autoclaved aerated concrete (AAC) wall laying (15 cm)()
YP.INS.DUVAR.008Autoclaved aerated concrete (AAC) wall laying (20 cm)()
YP.INS.DUVAR.009Pumice block wall laying (20 cm)()
YP.INS.DUVAR.010Supply and placement of lintel(m)
YP.INS.DUVAR.011In-wall tie beam concrete(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.