YP.INS.KALIP.005Bay/screed formwork (edge formwork)

Market Work Item · Construction · KALIP

Original Turkish name: Ano/şap kalıbı (kenar kalıbı)

Item No.YP.INS.KALIP.005
Unitm
ClassStandard
Estimated Unit Cost124,17 TL/mexcl. VAT

Scope

Construction of edge formwork to act as a screed guide along lean concrete/screed edges.

Components (3) · Quick Estimate

TypeNameUnitQty/mUnit Price (TL)Amount (TL)
MaterialFormwork timber (pine, 2nd class)9.166,6727,50
LabourFormwork carpentersaat466,6770,00
LabourUnskilled laborersaat333,3326,67
Subtotal (excl. VAT)124,17 TL
VAT (%20)24,83 TL
Grand Total149,00 TL

Component quantities are defaults; adjust them to your own job.

Items in the Same Group

YP.INS.KALIP.001Plain-faced timber formwork (foundation/shear wall)()
YP.INS.KALIP.002Plywood formwork (column/shear wall, smooth finish)()
YP.INS.KALIP.003Slab formwork (h ≤ 3 m, scaffolding included)()
YP.INS.KALIP.004Staircase formwork()

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.