YP.INS.KALIP.003 — Slab formwork (h ≤ 3 m, scaffolding included)

Market Work Item · Construction · KALIP

Original Turkish name: Döşeme kalıbı (h ≤ 3 m, iskele dahil)

Item No.YP.INS.KALIP.003
Unitm²
ClassStandard
Estimated Unit Cost1.064,11 TL/m²excl. VAT

Scope

Execution and removal of floor slab formwork, including shoring/scaffolding installation.

Components (5) · Quick Estimate

TypeNameUnitQty/m²Unit Price (TL)Amount (TL)
MaterialFormwork timber (pine, 2nd class)m³9.166,67137,50
MaterialFilm-faced plywood 18 mmm²835,90250,77
MachineryTelescopic prop set (rental)m²42,5042,50
LabourFormwork carpenterhr466,67466,67
LabourUnskilled laborerhr333,33166,67
Subtotal (excl. VAT)1.064,11 TL
VAT (%20)212,82 TL
Grand Total1.276,93 TL

Component quantities are defaults; adjust them to your own job.

Items in the Same Group

YP.INS.KALIP.001Plain-faced timber formwork (foundation/shear wall)(m²)
YP.INS.KALIP.002Plywood formwork (column/shear wall, smooth finish)(m²)
YP.INS.KALIP.004Staircase formwork(m²)
YP.INS.KALIP.005Bay/screed formwork (edge formwork)(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.