YP.INS.KIRIM.003Rubble bagging and carrying down to building entrance

Market Work Item · Construction · KIRIM

Original Turkish name: Moloz torbalama ve bina önüne indirme

CodeYP.INS.KIRIM.003
Unittorba
Estimated Unit Cost30,25 TL/torbaexcl. VAT

Scope

Bagging demolition rubble and carrying it to the front of the building. Debris transport is out of scope.

Components (3) · Quick Estimate

TypeNameUnitQty/torbaUnit Price (TL)Amount (TL)
MaterialDebris bagadet14,5014,50
LabourUnskilled laborersaat146,8011,74
ToolWheelbarrowadet2.005,004,01
Subtotal (excl. VAT)30,25 TL
VAT (%20)6,05 TL
Grand Total36,30 TL

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.KIRIM.001Brick wall demolition (non-load-bearing)()
YP.INS.KIRIM.002Plaster scraping (removal of old plaster)()
YP.INS.KIRIM.004Interior door removal (frame + leaf)(adet)
YP.INS.KIRIM.005Window removal(adet)
YP.INS.KIRIM.006Drywall ceiling/partition removal()
YP.INS.KIRIM.007Screed demolition()
YP.INS.KIRIM.008Kitchen cabinet removal (base + wall units)(takım)
YP.INS.KIRIM.009Complete bathroom demolition (sanitary ware + tiling)(takım)
YP.INS.KIRIM.010Core drilling in concrete wall/slab (Ø100-150)(adet)
YP.INS.KIRIM.011Balcony/stair railing removal(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.