YP.INS.KIRIM.001Brick wall demolition (non-load-bearing)

Market Work Item · Construction · KIRIM

Original Turkish name: Tuğla duvar kırımı (taşıyıcı olmayan)

Item No.YP.INS.KIRIM.001
Unit
Estimated Unit Cost239,26 TL/m²excl. VAT

Scope

Demolition of partition wall; rubble bagging is a separate item. Not applicable to load-bearing elements.

Components (6) · Quick Estimate

TypeNameUnitQty/m²Unit Price (TL)Amount (TL)
LabourUnskilled laborersaat333,33200,00
MachineryElectric rotary hammeradet3.860,2830,88
ToolMoil point and chisel setadet236,332,36
ToolSledgehammeradet748,833,74
ToolSafety gogglesadet150,891,51
ToolWork glovesadet76,360,76
Subtotal (excl. VAT)239,26 TL
VAT (%20)47,85 TL
Grand Total287,11 TL
Electric rotary hammerBuyMoil point and chisel set (Einhell)BuySledgehammer (Bosch)BuySafety goggles (Baymax)BuyWork gloves (Starline)Buy

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.KIRIM.002Plaster scraping (removal of old plaster)()
YP.INS.KIRIM.003Rubble bagging and carrying down to building entrance(torba)
YP.INS.KIRIM.004Interior door removal (frame + leaf)(adet)
YP.INS.KIRIM.005Window removal(adet)
YP.INS.KIRIM.006Drywall ceiling/partition removal()
YP.INS.KIRIM.007Screed demolition()
YP.INS.KIRIM.008Kitchen cabinet removal (base + wall units)(takım)
YP.INS.KIRIM.009Complete bathroom demolition (sanitary ware + tiling)(takım)
YP.INS.KIRIM.010Core drilling in concrete wall/slab (Ø100-150)(adet)
YP.INS.KIRIM.011Balcony/stair railing removal(m)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.