Market Work Item · Construction · HAFRIYAT
Original Turkish name: El ile moloz/toprak yükleme
| Item No. | YP.INS.HAFRIYAT.008 |
| Unit | m³ |
| Class | Standard |
| Estimated Unit Cost | 386,75 TL/m³excl. VAT |
Loading excavated material or debris manually onto a vehicle or container.
| Type | Name | Unit | Qty/m³ | Unit Price (TL) | Amount (TL) |
|---|---|---|---|---|---|
| Labour | Unskilled laborer | saat | 333,33 | 333,33 | |
| Tool | Construction shovel (with handle) | adet | 665,83 | 13,32 | |
| Tool | Wheelbarrow | adet | 2.005,00 | 40,10 | |
| Subtotal (excl. VAT) | 386,75 TL | ||||
| VAT (%20) | 77,35 TL | ||||
| Grand Total | 464,10 TL | ||||
Component quantities are defaults; adjust them to your own job.
Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.
Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.