YP.INS.HAFRIYAT.006Backfill + compaction with plate compactor

Market Work Item · Construction · HAFRIYAT

Original Turkish name: Dolgu + kompaktörlü sıkıştırma

Item No.YP.INS.HAFRIYAT.006
Unit
ClassStandard
Estimated Unit Cost363,15 TL/m³excl. VAT

Scope

Spreading the backfill in layers, watering, and compacting with a plate compactor.

Components (3) · Quick Estimate

TypeNameUnitQty/m³Unit Price (TL)Amount (TL)
LabourUnskilled laborersaat333,33266,66
MachineryPlate compactor (gasoline)adet41.583,3383,17
ToolConstruction shovel (with handle)adet665,8313,32
Subtotal (excl. VAT)363,15 TL
VAT (%20)72,63 TL
Grand Total435,78 TL
Construction shovel (with handle)Buy

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.HAFRIYAT.001Manual unconfined excavation()
YP.INS.HAFRIYAT.002Manual narrow-deep excavation (foundation/trench)()
YP.INS.HAFRIYAT.003Mechanical excavation (mini excavator)()
YP.INS.HAFRIYAT.004Mechanical excavation (excavator, wide area)()
YP.INS.HAFRIYAT.005Spreading backfill and manual compaction()
YP.INS.HAFRIYAT.007Supply and spreading of stabilized gravel/crushed stone()
YP.INS.HAFRIYAT.008Manual debris/soil loading()
YP.INS.HAFRIYAT.009Excavated soil transport (truck)(sefer)
YP.INS.HAFRIYAT.010Debris container (7-8 m³, hauling included)(sefer)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.