YP.INS.DEMIR.001Ribbed rebar work Ø8-Ø12 (cutting-bending-binding)

Market Work Item · Construction · DEMIR

Original Turkish name: Nervürlü demir işçiliği Ø8-Ø12 (kesme-bükme-bağlama)

Item No.YP.INS.DEMIR.001
Unitton
ClassStandard
Estimated Unit Cost41.792,60 TL/tonexcl. VAT

Scope

Cutting, bending, and binding of Ø8-Ø12 ribbed construction rebar according to its project. Rebar cost is included.

Components (6) · Quick Estimate

TypeNameUnitQty/tonUnit Price (TL)Amount (TL)
MaterialDeformed reinforcing steel bar Ø8-Ø12ton28.666,6730.100,00
MaterialTie wire / Binding wirekg100,55804,40
LabourRebar fixer / Ironworker mastersaat416,677.500,06
LabourUnskilled laborersaat333,333.333,30
ToolHacksawadet513,7525,69
ToolTowing hook / Rebar pulleradet582,9229,15
Subtotal (excl. VAT)41.792,60 TL
VAT (%20)8.358,52 TL
Grand Total50.151,12 TL
Tie wire / Binding wire (Gardener)BuyHacksaw (WorkPro)Buy

Component quantities are defaults; adjust them to your own job.

Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.

Items in the Same Group

YP.INS.DEMIR.002Ribbed rebar work Ø14-Ø16(ton)
YP.INS.DEMIR.003Laying and binding welded wire mesh(ton)
YP.INS.DEMIR.004Rebar dowelling (chemical anchoring Ø12-Ø16)(adet)

Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.