Market Work Item · Construction · CATI
Original Turkish name: Mahya kiremidi yenilenmesi
| Item No. | YP.INS.CATI.010 |
| Unit | m |
| Class | Standard |
| Estimated Unit Cost | 455,45 TL/mexcl. VAT |
Relaying the ridge line with mortar.
| Type | Name | Unit | Qty/m | Unit Price (TL) | Amount (TL) |
|---|---|---|---|---|---|
| Material | Ridge tile | adet | 54,00 | 162,00 | |
| Material | Ridge mortar | kg | 32,73 | 130,92 | |
| Labour | Roofing specialist | saat | 450,00 | 157,50 | |
| Tool | Trowel | adet | 268,78 | 1,34 | |
| Tool | Full body safety harness (parachutist type) | adet | 737,17 | 3,69 | |
| Subtotal (excl. VAT) | 455,45 TL | ||||
| VAT (%20) | 91,09 TL | ||||
| Grand Total | 546,54 TL | ||||
Component quantities are defaults; adjust them to your own job.
Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.
Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.