Market Work Item · Construction · SUYALITIM
Original Turkish name: Temel perde dıştan su yalıtımı (sürme bitüm + drenaj levhası)
| Item No. | YP.INS.SUYALITIM.006 |
| Unit | m² |
| Class | Standard |
| Estimated Unit Cost | 650,69 TL/m²excl. VAT |
Primer and two coats of two-component rubber-bitumen coating on the external foundation wall, protected with HDPE dimpled drainage board. Drain pipe run is a separate item.
| Type | Name | Unit | Qty/m² | Unit Price (TL) | Amount (TL) |
|---|---|---|---|---|---|
| Material | Bitumen primer | L | 51,56 | 20,62 | |
| Material | Rubber-bitumen liquid waterproofing, two-component | kg | 86,85 | 303,97 | |
| Material | HDPE dimpled drainage board, 400 g/m² | m² | 55,56 | 61,12 | |
| Labour | Plasterer | saat | 466,67 | 210,00 | |
| Labour | Unskilled laborer | saat | 333,33 | 50,00 | |
| Tool | Waterproofing brush | adet | 248,83 | 4,98 | |
| Subtotal (excl. VAT) | 650,69 TL | ||||
| VAT (%20) | 130,14 TL | ||||
| Grand Total | 780,83 TL | ||||
Component quantities are defaults; adjust them to your own job.
Tool rows are included with a depreciation quantity; set the quantity to 0 if not needed.
Prices are estimated market averages; they do not belong to any single seller or platform and are not a binding quotation. Data is compiled by yap-poz.com through independent market research; it is not official unit price data.